As the new school year begins, construction on campus continues.Here is an update on some of the key projects. For moreinformation, visit http://smu.edu/construction.
Dedman Center for Lifetime Sports
Location: Airline Road and Binkley Avenue
The student-funded, nearly 100,000 square foot expansion of thisfacility will include two basketball courts, an extended track, aclimbing wall, a bouldering wall, improved dressing rooms andfitness facilities, an indoor soccer field, swimming facilities andother improvements. The existing center, as well as the CincoCenter, will remain open throughout construction.
Expected completion date: expansion: Sept. 2005; renovation: May2006
James M. Collins Executive Education Center
Location: Binkley Avenue and Ownby Drive
This new facility will house Executive Education and provideoffices and classrooms for the Cox School of Business’Executive MBA program, the KPMG Institute for Corporate Governanceand the Southwestern Graduate School of Banking.
Be aware of increased truck traffic in the area and walk onsidewalks, not in the street. Ownby is one-way southbound betweenDyer and Binkley.
Expected completion date: March 2005
Perkins Administration Building
Location: University Boulevard and Boaz Lane
Renovations will provide new office space for variousdepartments, including Development and External Affairs.
Expected completion date: early Sept. 2004
Fincher Building
Location: between Bishop Boulevard and Ownby Drive in the CoxSchool of Business
Hallways, restrooms and the lobby are being renovated, includingnew carpet, tile and fixtures.
Expected completion date: early Sept. 2004
Dyer Street improvements
Location: 3000 block of Dyer Street
Preparations for the new Sigma Alpha Epsilon and Lambda ChiAlpha houses and a parking lot include rerouting Dyer to connectwith McFarlin Boulevard, utility work, grading the site, paving theparking lot and building an 8-foot brick wall along Dublin betweenDyer and University.
Be aware of increased truck traffic and construction activitiesbetween 7 a.m. and 7 p.m. Monday through Friday. This is a jointproject between SMU and University Park.
Expected completion date: on Dyer: Oct. 2004; otherconstruction: summer 2005
Sigma Alpha Epsilon and Lambda Chi Alpha houses
Location: Dyer Street
These two new houses are scheduled to be built before theexisting houses and Letterman Hall on Binkley between Ownby andAirline are demolished in fall 2005 to make way for a parkinggarage.
Expected construction start date: Oct. 2004
Expected completion date: Aug. 2005
Sigma Phi Epsilon house
Location: SMU Boulevard
Renovations and additions include a redesigned floor plan andnew façade. The house will go from sleeping nine to 22.
Expected completion date: Jan. 2005
Fondren Science Building
Location: Daniel Avenue
Renovations included modern office and lab space.
Completed: summer 2004
West sidewalks
Should be completed by Friday
Lovers Lane detour
Location: Lovers Lane between Hillcrest Avenue and NorthCentral Expressway
This University Park project involves reconstructing the streetand utilities such as water lines and sanitary and storm sewers. Itwill also include new traffic signals at Boedeker and Airline, aswell as decorative streetlights at every intersection.
Expected completion date: Oct. 2005
This is part of an occasional series.